Open Access Solar in MP:
A Plain-English Guide
What it is, how the charges work, why the numbers still deliver a 40% saving, and why MP industry is moving fast on this right now.
MP Regulatory Reference
Open Access Solar — MP Policy at a Glance
- Minimum contracted demand: 1 MW (Long-Term Open Access)
- Grid connection: 33 kV or above
- Rooftop behind-the-meter: from 500 kW (no OA charges)
- Application submitted to SLDC; decision within 30 days
- Transmission charges: ~₹0.30–0.45/kWh
- Wheeling charges: ~₹0.50–0.60/kWh
- CSS: waived in Green Zone clusters (Pithampur, Mandideep, Dewas, Indore SEZ)
- RPO: OA units count towards annual compliance
Charges set annually by MPERC. Green Zone benefits under MP RE Policy 2025. Scroll down for the full cost analysis and how OA compares to rooftop solar.
The Basics
What Is Open Access Solar?
India's electricity grid has traditionally been a one-way system: power plants generate, DISCOMs (state utilities) distribute, and consumers pay whatever tariff the regulator sets. Open Access breaks this monopoly for large consumers.
Under Open Access, a qualifying industrial consumer can contract electricity directly from a renewable generator, like an r-solar plant, at a negotiated tariff. They continue using the existing grid infrastructure (wires, substations) and pay regulated charges for that usage, but the energy itself is sourced from their contracted generator.
Two types of Open Access
Scheduling-based, month-to-month. Good for testing the market. Higher regulatory risk. Not suitable for long-term project financing.
Granted for 25 years under a signed PPA. Enables project-level debt financing. Predictable, bankable, and the foundation of our RESCO/OPEX model.
Eligibility & Flow
Who Qualifies and How It Works
In Madhya Pradesh, Open Access is available to consumers connected at 33 kV or above with a contracted demand of 1 MW or more. For smaller consumers (down to 500 kW), behind-the-meter rooftop OPEX is the equivalent model.
Consumer Applies for Open Access
The industrial consumer (or their developer, us) applies to the SLDC (State Load Dispatch Centre) for Open Access approval. For LTOA, this requires a signed PPA to be attached.
SLDC Grants Connectivity & Scheduling Rights
The SLDC allocates transmission capacity and assigns scheduling rights. r-solar's plant gets a generation schedule tied to the consumer's load pattern.
Plant Generates, Grid Wheels the Power
r-solar's plant generates solar electricity. It is injected into the 33 kV grid and "wheeled" to the consumer's facility. The grid acts as the transport network.
Consumer Pays Two Bills
One invoice from r-solar at ₹4.50/kWh for the units consumed. A reduced DISCOM bill for the remaining grid top-up (nights, cloudy days, and demand above the plant's output).
MP Eligibility Checklist
For LTOA ground-mount. Rooftop behind-the-meter from 500 kW.
11 kV consumers can upgrade connection. r-solar helps assess feasibility.
Critical for grid evacuation feasibility. We check this at site qualification.
SLDC requires a clean dues certificate before granting OA status.
Our focus is MP (MPERC jurisdiction). Each state has its own OA regulations.
The Numbers
Open Access Charges in MP: Fully Decoded
These are the MPERC-regulated charges that apply when power is wheeled from a generator to a consumer via the grid. They are transparent, regulated, and built into our PPA pricing model.
MPERC FY 2025–26 · 33 kV Consumer
What Each Charge Covers
Wheeling Charge: ₹0.18/kWh
Paid to the DISCOM for using their local distribution infrastructure to deliver power from the 33 kV network to the consumer's premises. Think of it as the "last mile" delivery fee.
Transmission Charge: ₹0.86/kWh
Paid to MPPTCL (MP Power Transmission Company) for using the high-voltage transmission network (220 kV / 400 kV lines and substations) to carry power from the generation site to the consumer's grid zone.
Cross-Subsidy Surcharge (CSS): ~₹0.20/kWh
Compensates the DISCOM for loss of a paying industrial customer (who cross-subsidises residential/agricultural consumers). The CSS is set by MPERC annually and is waived in designated Green Zone industrial areas.
Side by Side
Grid vs Open Access PPA
Current Grid (DISCOM)
/kWh, and rising ~10%/yr
- closeTariff hike every year
- closeNo RPO compliance benefit
- closeNo ESG credentials
- closeFull exposure to energy cost inflation
r-solar Open Access PPA
/kWh, fixed for 25 years
- checkFixed tariff, immune to hikes
- checkSatisfies 30% RPO mandate
- checkScope 2 reduction for ESG
- checkZero capex for the consumer
Based on MPERC FY 2025-26 tariff order. Indicative estimates; actual savings modelled per facility.
Regulatory Tailwinds
RPO Mandate & Green Zone Benefits
Two regulatory factors are making Open Access solar not just attractive, but compulsory for large MP industrial consumers.
MP RE Policy 2025: 30% RPO Mandate
Large industrial units (obligated entities) must source a minimum 30% of total electricity consumption from renewable sources by FY2027, rising to 50% by FY2030. Non-compliance attracts financial penalties payable to MPERC.
An Open Access solar PPA from r-solar directly satisfies this obligation. We provide monthly generation certificates that your team submits in your annual RPO compliance filing.
Green Zone Benefits
MP RE Policy 2025 designates certain industrial corridors as Green Zones, including Pithampur, Mandideep, Dewas, and Indore SEZ. Green Zone consumers receive:
- Electricity duty exemption on renewable energy consumed
- Waiver of Cross-Subsidy Surcharge (CSS)
- Land rate rebates for solar projects in approved industrial corridors
- Priority SLDC scheduling for Open Access
ESG & Scope 2 Reporting
Export-oriented manufacturers face increasing scrutiny from international buyers on Scope 2 (purchased electricity) emissions. An Open Access solar PPA provides verifiable, third-party-certified evidence of renewable energy sourcing, directly reportable under GHG Protocol, CDP, and India's BRSR (Business Responsibility and Sustainability Report) framework.
7.8 GW Added in India in 2025
India added a record 7.8 GW of new Open Access solar in 2025. Institutional buyers (Amplus, ReNew, Fourth Partner Energy) are actively acquiring portfolios of PPAs in MP. The platform sale market is real, which is why r-solar is building toward an institutional exit at 100 MW.
Why r-solar
Our Structural Advantage in MP
National developers operate from Delhi or Bangalore. We operate from Barwani and Indore. That difference matters more than it sounds.
Local Roots
1,000+ installations in MP. Existing relationships with factory owners, DISCOM officials, and local EPC contractors in the Barwani–Sendhwa–Indore belt.
Faster Execution
LOI to commissioning in 6 months for a 5–10 MW plant. National players take 12–18 months. Our local approvals track record and EPC partnerships (Solluz, ISES Indore) drive this speed.
Tech-Enabled O&M
IoT data logger installed from Day 1. Real-time generation data, automated billing, and monthly compliance reports, visible to the off-taker via our dashboard.
25-Year Partnership
We own the asset. Our incentives are perfectly aligned with yours: more generation = more revenue for us = more savings for you. We're not just an installer who walks away.
FAQ
Frequently Asked Questions
Ready to See If Your Facility Qualifies?
Get a custom savings model based on your actual bills. No commitment. Response in 48 hours.